Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

Exam PMP All Questions
Exam PMP All Questions

View all questions & answers for the PMP exam

PMI Project-Management-Professional PMP Question # 45 Topic 5 Discussion

PMP Exam Topic 5 Question 45 Discussion:
Question #: 45
Topic #: 5

A project manager is involved with a project to remodel a long-used product. There are no proper records for the original design and execution of the original product. The stakeholders doubt that the remodel can be accomplished without this information and are hesitant to provide support for the project.

What should the project manager do?


A.

Acknowledge the stakeholders’ concerns with open dialogues and realign the project with stakeholder requirements and past lessons learned.


B.

Solicit a larger reserve for cost and time and manage the stakeholders’ expectations.


C.

Create a plan to inform stakeholders on the progress so they are able to see that the project can succeed,


D.

Share the threats of not updating old solutions and ask stakeholders to be patient with any inconveniences.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.