A project is nearing completion. The sponsor is already asking the project management office (PMO) when the project manager will be assigned to host a planning session for a new initiative.
What should the project manager do next?
A.
Review organizational process assets (OPAs) for clarity.
B.
Document lessons learned before closing.
C.
Consult the project charter for next steps.
D.
Confirm the definition of done (DoD) has been met.
As per the Project Management Professional (PMP) guidelines, when a project is nearing completion, the project manager should first confirm that the definition of done (DoD) has been met. This means that all project deliverables have been completed and approved. Only after this confirmation, the project manager can move on to the next steps such as documenting lessons learned or planning for a new initiative.
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit