PMI Project-Management-Professional PMP Question # 49 Topic 5 Discussion

PMP Exam Topic 5 Question 49 Discussion:
Question #: 49
Topic #: 5

A project is nearing completion. The sponsor is already asking the project management office (PMO) when the project manager will be assigned to host a planning session for a new initiative.

What should the project manager do next?


A.

Review organizational process assets (OPAs) for clarity.


B.

Document lessons learned before closing.


C.

Consult the project charter for next steps.


D.

Confirm the definition of done (DoD) has been met.