PMI Project-Management-Professional PMP Question # 484 Topic 50 Discussion

PMP Exam Topic 50 Question 484 Discussion:
Question #: 484
Topic #: 50

A key project stakeholder does not attend any of the project meetings and is

providing false information that the project team is not delivering on time. What should the

project manager do to address this situation?


A.

Create a new communication artifact for the key stakeholder.


B.

Email the latest status report to the key stakeholder.


C.

Share the meeting recordings with the key stakeholder.


D.

Discuss communication needs with the key stakeholder.