A project manager is managing two integrated projects in a program A key integration point is misaligned, which has resulted in delays. One of the team's integration leads is a subject matter expert (SME) m this integration area. The other team's integration lead is not a SME but is more senior and has worked on the project longer Both team leads are blaming each other

What should the project manager do first to resolve this situation?


A.

Assign the resolution of the issue to the senior integration lead who has worked on the project longer


B.

Meet with both integration leads to understand the root cause and determine a resolution


C.

Escalate the issue to the program architect who developed the integration plan


D.

Assign the resolution of this issue to the integration lead who is a SME