PMI Project-Management-Professional PMP Question # 491 Topic 50 Discussion

PMP Exam Topic 50 Question 491 Discussion:
Question #: 491
Topic #: 50

An equipment vendor will implement a new production line for a client company. The year-long project will include 2- to 4-month long iterations; however, the client's project manager has no agile experience.

How should the project manager ensure that the client is effectively represented in the daily meetings?


A.

Recommend agile training programs that best suit the client project manager's schedule.


B.

Realign the project to a predictive approach to ensure optimal collaboration between the teams.


C.

Propose a session tor essential agile Knowledge transfer for the client team to align with the daily meeting goals


D.

Provide the client project manager with agile best practice documents and web resources.