PMI Project-Management-Professional PMP Question # 492 Topic 50 Discussion

PMP Exam Topic 50 Question 492 Discussion:
Question #: 492
Topic #: 50

A project manager is assigned to a new project and is allocated with virtual team

members. Later, two more members from a recently acquired company join as additional

resources to the project team.

In order to ensure that there are no potential misunderstandings, what should the project

manager do?


A.

Send an email update to existing team members about the addition of the new team

members.


B.

Set up a weekly meeting with the new team members for a couple of months.


C.

Request the transfer of the new members to another project, citing a risk of confusion.


D.

Update and share the guideline document dealing with team communication.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.