Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam PMP All Questions
Exam PMP All Questions

View all questions & answers for the PMP exam

PMI Project-Management-Professional PMP Question # 497 Topic 51 Discussion

PMP Exam Topic 51 Question 497 Discussion:
Question #: 497
Topic #: 51

At the end of a project, one of the suppliers is facing financial difficulties and is

pushing the project manager to obtain financial, legal, and administrative approval in order to

communicate formal project closure and ensure the transfer of liability. What should the

project manager do next?


A.

Compare the achieved results to the contract requirements.


B.

Make the final payment as the project is completed.


C.

Transfer the remaining variances and close the project.


D.

Escalate to higher management to expedite the approval.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.