A team is working on a hybrid project. Due to different interpretations of the project requirements, the deliverables are not aligned to the expectations. What steps should the project manager have taken to prevent this?
A.
Update the project management plan in order to get back on track.
B.
Ensure the team receives continuous feedback from customers users.
C.
Submit a change request to adjust the project scope.
D.
Ensure the team understands all additional project requirements.
A hybrid project is a project that combines predictive and adaptive approaches. In such a project, the project manager should ensure that the team receives continuous feedback from customers users to validate the alignment of the deliverables with the expectations. This is a key practice of agile and adaptive methods, which aim to maximize customer satisfaction and value delivery. Updating the project management plan, submitting a change request, or ensuring the team understands all additional project requirements are not steps that would prevent the misalignment of the deliverables with the expectations, but rather actions that could be taken after the problem has occurred.Ā References: [PMI Agile Practice Guide], page 14; [PMBOKĀ® Guide 6th Edition], page 19.
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit