PMI Project-Management-Professional PMP Question # 500 Topic 51 Discussion

PMP Exam Topic 51 Question 500 Discussion:
Question #: 500
Topic #: 51

A team is working on a hybrid project. Due to different interpretations of the project requirements, the deliverables are not aligned to the expectations. What steps should the project manager have taken to prevent this?


A.

Update the project management plan in order to get back on track.


B.

Ensure the team receives continuous feedback from customers users.


C.

Submit a change request to adjust the project scope.


D.

Ensure the team understands all additional project requirements.