PMI Project-Management-Professional PMP Question # 501 Topic 51 Discussion

PMP Exam Topic 51 Question 501 Discussion:
Question #: 501
Topic #: 51

An issue reoccurs six months after a project's go-live date despite being resolved

during the project life cycle. What should the project manager have done in the previous

phase to avoid this issue?


A.

Ensured the project team documented lessons learned about the issue


B.

Ensured the project team applied a long-term solution for the issue


C.

Asked the project team to conduct more testing with users


D.

Discussed the issue with the stakeholders