Question #: 505
Topic #: 51

A complex, high-value agile project includes sprint demonstrations with the customer

every four weeks. Executive management is concerned about the project's progress and

wants more frequent updates on the project status.

What should the project manager do?


A.

Inform executive management that the customer is made aware of the status during

the sprint demo.


B.

Prepare a weekly status report and share it with executive management every week.


C.

Inform executive management about agile principles and processes that are followed

in the project.


D.

Ask the team to prepare and share the status report with executive management every

week.