PMI Project-Management-Professional PMP Question # 513 Topic 53 Discussion

PMP Exam Topic 53 Question 513 Discussion:
Question #: 513
Topic #: 53

A project manager has been assigned to complete a worksite project that was started by a different project manager. The project is now in the execution stage. Upon careful review, the project manager realizes that the local community was not included in the stakeholder register, which has resulted in extreme opposition from the community.

How should the project manager handle this issue?


A.

Disregard these stakeholders since the relevant documents have been secured to execute this project.


B.

Update the stakeholder register and risk management plan.


C.

Update the stakeholder register and revise the stakeholder engagement plan.


D.

Explain to the community members why they were not included as stakeholders for the project.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.