Question #: 519
Topic #: 53

A project manager is assigned to a new project. The project management office

(PMO) and the project manager agree that this is the right opportunity to include daily

standup meetings. The project team has never used such tools, and a few members are

challenging the decision.

What should the project manager do in this situation?


A.

Engage an external vendor to perform the design phase under an iterative approach.


B.

Request that new team members familiar with iterative approaches be assigned to this project.


C.

Update the project schedule to consider a daily standup as part of the project design phase.


D.

Define the ground rules, responsibilities, and conflict management strategies.