PMI Project-Management-Professional PMP Question # 520 Topic 53 Discussion

PMP Exam Topic 53 Question 520 Discussion:
Question #: 520
Topic #: 53

A project manager is managing a project with a hybrid approach and has requested a senior team member to perform a quantitative risk analysis The team member responds that they do not have the knowledge to perform such an analysis.

What should the project manager do?


A.

Contact the project management office (PMO) and request them to assign another team member who has the knowledge to perform this task to the team


B.

Escalate the issue to the functional manager


C.

Help the team member to perform the quantitative risk analysis through coaching, mentoring and training


D.

Perform the quantitative risk analysis for the team member.