Question #: 524
Topic #: 54

During project execution, a project manager discovers that the budget at completion has shifted significantly and is higher than expected.

What should the project manager do?


A.

Adjust the original budget estimates with the current cost variance.


B.

Negotiate the project changes and adjust stakeholder expectations.


C.

Perform a root cause analysis of the project performance.


D.

Review the activity duration to reforecast the project completion date.