Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam PMP All Questions
Exam PMP All Questions

View all questions & answers for the PMP exam

PMI Project-Management-Professional PMP Question # 533 Topic 55 Discussion

PMP Exam Topic 55 Question 533 Discussion:
Question #: 533
Topic #: 55

A company is involved in a mining project. There are some external stakeholders with no knowledge of the mining industry.

How should the project manager communicate the organizational culture and project goal to these stakeholders?


A.

Hire a company to advertise the project and company through a media outlet.


B.

Prepare a report outlining the organizational structure and project parameters.


C.

Take the stakeholders out informally and verbally brief them about the organization and project.


D.

Ask a team member to directly address the information needs of the stakeholders.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.