An intern is replacing a critical resource midway through a sprint To help the intern get up to speed, the project manager assigns a senior engineer in the team as the intern's mentor Two months later, the project goes into critical status, delaying the release milestone by a month.

What should the project manager have done to avoid this scenario?


A.

Convinced the critical resource to remain on the project.


B.

Requested an experienced resource as a replacement


C.

Allocated additional time for mentoring


D.

Negotiated additional time to complete the project