PMI Project-Management-Professional PMP Question # 540 Topic 55 Discussion

PMP Exam Topic 55 Question 540 Discussion:
Question #: 540
Topic #: 55

A major project is unable to access the US$12 million funding allocated for the project. This prevents the start of the procurement process and is already leading to costly delays.

What should the project manager do?


A.

Escalate to the project steering committee.


B.

Invite the finance department to the next project demo.


C.

Review the project requirements.


D.

Use the currently available resources.