PMI Project-Management-Professional PMP Question # 541 Topic 56 Discussion

PMP Exam Topic 56 Question 541 Discussion:
Question #: 541
Topic #: 56

While preparing an earned value analysis (EVA) for the sponsor, the project manager provided this information in the latest project report:

    Approved Work Package Cost Estimates: US$9,500

    Contingency reserves: $500 %

    Management reserves: 10% of contingency reserves

    Percent complete of the project: 50%

    Planned percent of the project: 40%

    Actual costs of the project: US$4,500

What is accurate about the project status?


A.

The actual work is 25% more than the planned work.


B.

The project cost is 10% lower than planned.


C.

The actual work is 25% less than the planned work.


D.

The project cost is 10% higher than planned.