PMI Project-Management-Professional PMP Question # 545 Topic 56 Discussion

PMP Exam Topic 56 Question 545 Discussion:
Question #: 545
Topic #: 56

A project manager has noticed that the performance of a new team member has increased dramatically over the past few months The project manager has been measuring this team member's performance through the cost performance index (CPl) and schedule performance index (SPl) of work packages. The project manager has also assigned new. unrelated work packages to this team member The project manager wants to formally record the team member's success in the project documentation

What should the project manager do?


A.

Attach a note to the project management plan about the team member


B.

Hold a project team meeting about the team member's contribution and take minutes


C.

Record the team member's contribution in the responsibility assignment matrix (RAM)


D.

Send a communication to management recognizing the team member's contributions