A project manager scheduled a session to identify risks on the current project. Most of the stakeholders did not attend the meeting, although they previously confirmed their attendance.

How should the project manager proceed in order to complete the risk register?


A.

Cancel the meeting and create the risk register using the project documents.


B.

Continue the meeting and send the updated risk register to all stakeholders.


C.

Run the meeting and follow up with each one of the absent stakeholders to get their input.


D.

Escalate the issue of stakeholders not attending the meeting to the project sponsor.