PMI Project-Management-Professional PMP Question # 565 Topic 58 Discussion

PMP Exam Topic 58 Question 565 Discussion:
Question #: 565
Topic #: 58

A project manager is working on the budget for a long-term project. The project manager creates a work breakdown structure (WBS) and estimates the cost for each work package based on past projects.

What else does the project manager need to do before determining the budget baseline?


A.

Look at a previous project to ensure the budget totals match.


B.

Require all stakeholders to review and approve the estimates.


C.

Revise the project timeline and scope based on the WBS.


D.

Add contingency into the budget for inflation and other changes.