PMI Project-Management-Professional PMP Question # 568 Topic 58 Discussion

PMP Exam Topic 58 Question 568 Discussion:
Question #: 568
Topic #: 58

During a project review meeting, several project team members expressed that they did not have an understanding of the benefits of certain features for the project What should the project manager do next?


A.

Review the project scope statement


B.

Confirm ownership for ongoing value realization


C.

Escalate the issue to the project sponsor


D.

Appraise the stakeholders of value gain progress