Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam PMP All Questions
Exam PMP All Questions

View all questions & answers for the PMP exam

PMI Project-Management-Professional PMP Question # 573 Topic 59 Discussion

PMP Exam Topic 59 Question 573 Discussion:
Question #: 573
Topic #: 59

A project manager has just been assigned to a team that is developing a new design product. The work breakdown structure (VW/BS) has been created and the activities have been assigned to the team members. The project manager finds that there are activities that could be completed sooner by other team members. If the current assignments are left as is, the project could be delayed 2 weeks.

What should the project manager do in this situation?


A.

Review the work allocation and reassign some tasks to shorten the critical path.


B.

Maintain the task assignments as planned and compress the other tasks to keep the project on schedule.


C.

Ask the team members to work overtime to finish the tasks on time according to the schedule.


D.

Keep the task assignments unchanged since the project management plan has been approved.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.