Question #: 578
Topic #: 59

A project manager is managing the scope of the project and creating a work breakdown structure (WBS) with the team members. How should the project manager organize the WBS?


A.

Cost oriented


B.

Deliverable oriented


C.

Customer oriented


D.

Team oriented