PMI Project-Management-Professional PMP Question # 57 Topic 6 Discussion

PMP Exam Topic 6 Question 57 Discussion:
Question #: 57
Topic #: 6

A new solution is being deployed in countries A B and C. This solution will allow the countries to propose new services to their customers Country A has asked for a change in the solution m order to comply with its own customer market

What should the project manager in charge of the deployment in country A do?


A.

Accept the change request from country A and reschedule the deployment project for country A.


B.

Take the request into account and ask the sponsor to inform countries B and C about the change


C.

Ask country A to submit a change request that will be analyzed along with countries B and C


D.

Refuse country As request as there is no time for the change as deployment has already begun