PMI Project-Management-Professional PMP Question # 587 Topic 60 Discussion

PMP Exam Topic 60 Question 587 Discussion:
Question #: 587
Topic #: 60

Two team members were recently released from a project because the customer reduced the budget. However, the agile team is still receiving the same, if not more, work requirements as before.

How should the agile project leader resolve this situation?


A.

Update the restriction log with the new team capacity.


B.

Explain the new project requirements to the team.


C.

Update the project budget with the released team members.


D.

Explain the new team velocity to the customer.