PMI Project-Management-Professional PMP Question # 589 Topic 60 Discussion

PMP Exam Topic 60 Question 589 Discussion:
Question #: 589
Topic #: 60

A project manager receives feedback from the customer's leadership team regarding their annoyance about the frequency of email updates. What should the project manager have done first to prevent this?


A.

Understood the customer's company culture


B.

Updated the communications management plan


C.

Analyzed customer interest and engagement


D.

Scheduled weekly update meetings