PMI Project-Management-Professional PMP Question # 590 Topic 60 Discussion

PMP Exam Topic 60 Question 590 Discussion:
Question #: 590
Topic #: 60

An organization has recently decided to switch from a predictive to an agile delivery approach. The one ongoing project will still be led by a project manager. The agile teams for that project have not produced any documentation.

What should the project manager of the ongoing project do?


A.

Submit new user stories to the product owner in order to put documentation in the product backlog.


B.

Introduce a document management tool to support the agile teams in preparing the documentation.


C.

Check with the agile teams to see if the project manager's understanding of the Agile Manifesto is correct.


D.

Add an additional team member to take up the role of scribe for the required documentation.