PMI Project-Management-Professional PMP Question # 601 Topic 62 Discussion

PMP Exam Topic 62 Question 601 Discussion:
Question #: 601
Topic #: 62

A company's project management office (PMO) has started to implement iterative tools. The project manager is starting a new project and has

identified an opportunity to use the new tools. There is disagreement among stakeholders about the use of the adaptive tool.

What should the project manager do first?


A.

Investigate the reasons for the disagreement to understand the gap among the stakeholders and search for consensus.


B.

Discuss the situation with the stakeholders to evaluate other adaptive tools for the project.


C.

Schedule training sessions for the stakeholders on the benefits of the adaptive tools.


D.

Update the risk register and escalate the disagreement to the project sponsor and distribute the status to the team.