PMI Project-Management-Professional PMP Question # 605 Topic 62 Discussion

PMP Exam Topic 62 Question 605 Discussion:
Question #: 605
Topic #: 62

A project manager is leading a project that is at 90% completion. One of the key stakeholders requests a certification program to be included as part of the project. Another stakeholder disagrees and informs the project team that there should be no change to the project management plan since the project is nearing completion.

What should the project manager do?


A.

Update the project management plan and adjust the project budget with this change request.


B.

Raise a change request to the change control board (CCB) and inform the project sponsor about the change.


C.

Ask the key stakeholder to take the lead in handling the request since they are more knowledgeable.


D.

Request a meeting with the stakeholders and their team members to inform them about this change.