PMI Project-Management-Professional PMP Question # 613 Topic 63 Discussion

PMP Exam Topic 63 Question 613 Discussion:
Question #: 613
Topic #: 63

A project manager is facilitating a project steering committee meeting where the prioritization of work items in the backlog is being discussed. The

engineering executive wants to prioritize features based on level of effort, completing the smallest items first. The quality executive wants to

complete the most complex tasks first to have adequate time to ensure a quality product is delivered. The compliance officer wants to complete

items with associated regulatory components as they are essential items.

How should the project manager prioritize the work items?


A.

Complete tasks associated with regulatory components as the team cannot deliver business value that does not adhere to compliance

regulations.


B.

Ensure that the team assesses opportunities to deliver the highest business value items incrementally.


C.

Ensure that the project value is within the quality guidelines by prioritizing and completing intricate tasks earlier in the project.


D.

Complete the smaller tasks first to allow the team opportunities to prototype and evaluate development processes.