During an agile project a project manager lost one of the resources, and at the same lime, uncovered new requirements, which were added to the backlog What should the project manager do next?


A.

Reevaluate the project schedule as the velocity will be impacted by the loss of resources


B.

Reevaluate the backlog priority with the product owner since the velocity has been impacted


C.

Reevaluate the scope of the current iteration to keep the same velocity and timeline


D.

Reevaluate the velocity as the iteration duration will be impacted by new requirements