PMI Project-Management-Professional PMP Question # 628 Topic 64 Discussion

PMP Exam Topic 64 Question 628 Discussion:
Question #: 628
Topic #: 64

A project manager is managing a large project. A stakeholder has just discovered a new risk that has not been identified in earlier stages.

What should the project manager do?


A.

Communicate the risk to the steering committee and request a mitigation plan from senior management.


B.

Perform a risk analysis directly with the stakeholder who raised the risk and update the risk register.


C.

Confirm to the stakeholder that the risk register has been completed and validated by all stakeholders.


D.

Add the risk to the risk register and reevaluate the register with help from the project team and stakeholders.