Question #: 637
Topic #: 65

A project manager has been assigned to a project where the budget is very tight. Incurring extra costs is not an option.

What should the project manager do to manage this situation?


A.

File a change request to make the customer billable for all extra costs incurred for the project.


B.

Ask the accounting department to forward all project expenses to the project manager's email.


C.

Monitor the budget for the project continually and anticipate any issues if possible.


D.

Ask the project resources to finish their assignments in less time than originally planned.