PMI Project-Management-Professional PMP Question # 642 Topic 66 Discussion

PMP Exam Topic 66 Question 642 Discussion:
Question #: 642
Topic #: 66

During a system demo, a project stakeholder rejects the features completed from the most recent user stories. According to the stakeholder, the product does not meet the

quality standards required by regulations.

What should the project manager have done to avoid this?


A.

Reviewed with the product owner that all the stories worked on in the iteration were in the project backlog


B.

Ensured that the project sponsor understood the scope of the project to avoid any future complaints


C.

Reviewed with the product owner that all acceptance criteria were met for the stories worked on in the iteration


D.

Ensured the stakeholder concerns were properly addressed in the iteration to avoid future setbacks