PMI Project-Management-Professional PMP Question # 643 Topic 66 Discussion

PMP Exam Topic 66 Question 643 Discussion:
Question #: 643
Topic #: 66

A human resources (HR) cost report was disclosed, by error, to all members of the project team. This situation generated a conflict between the team members about differences in their salaries.

What should the project manager have done to avoid this situation?


A.

Ensured reports with significant information were not included in the communications management plan


B.

Defined the appropriate recipients for the report in the communications management plan


C.

Included noncompliance punishment measures in the communications management plan


D.

Validated the information and the appropriate recipients per the communications management plan


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.