Question #: 653
Topic #: 67

The project manager's firm is executing a construction project. The project is stalled due to reemerging conflicts and misunderstandings among stakeholders.

What should the project manager do to ensure a smooth start and completion of the project?


A.

Conduct an on-site survey, start the project to avoid any undue delays, and ensure costs are under control


B.

Invite all the stakeholders to a change control board (CCB) meeting, share feedback and facts, and come to a consensus.


C.

Advise the firm to cancel the project due to misunderstandings among the stakeholders and the associated risks.


D.

Determine the root cause of the misunderstandings, get all parties to reach a consensus, and help to implement the outcome.