PMI Project-Management-Professional PMP Question # 654 Topic 67 Discussion

PMP Exam Topic 67 Question 654 Discussion:
Question #: 654
Topic #: 67

Just as a team reaches a mutual consensus on a preferred design, a stakeholder submits a request to add new features that enhance the

company’s competitive advantage. What should the project manager do?


A.

Reject all requested changes and bypass the company's change control process.


B.

Encourage the project team to add premium features to impress the client.


C.

Start the process to include the new features of the product on the next iteration.


D.

Allow all requested changes and bypass the company's change control process.