PMI Project-Management-Professional PMP Question # 655 Topic 67 Discussion

PMP Exam Topic 67 Question 655 Discussion:
Question #: 655
Topic #: 67

A project manager is made aware that there are defects in the parts provided by a supplier, which are causing delays in the testing phase. The supplier claims that all parts have been delivered as per the contract. If the defects are not fixed by the supplier within one week, the product release will be impacted.

What should the project manager do?


A.

Escalate this issue to senior management, as the supplier is not following the procurement contract.


B.

Request a revision of the procurement contract to include specifications for the parts.


C.

Request a cancellation of the procurement contract with the supplier and impose a penalty.


D.

Review the procurement contract and ask the supplier to negotiate a solution.