Weekend Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam PMP All Questions
Exam PMP All Questions

View all questions & answers for the PMP exam

PMI Project-Management-Professional PMP Question # 660 Topic 67 Discussion

PMP Exam Topic 67 Question 660 Discussion:
Question #: 660
Topic #: 67

A project manager is managing a technical project that requires intensive documentation as part of the key deliverables. Ina project review meeting, a key stakeholder reports that the latest documentation provided by the project manager includes a reference to unrelated products.

What should the project manager do?


A.

Ask the project management office (PMO) to support and review all deliverables.


B.

Log the issue in the risk register and the issue log.


C.

Assign a technical writer to the project.


D.

Develop a standard for document quality control.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.