Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam PMP All Questions
Exam PMP All Questions

View all questions & answers for the PMP exam

PMI Project-Management-Professional PMP Question # 664 Topic 68 Discussion

PMP Exam Topic 68 Question 664 Discussion:
Question #: 664
Topic #: 68

A project's business case was just approved and the project manager is creating the benefits management plan. It is unclear how the benefits from the project align with the organization's vision.

What should the project manager do first to verify alignment?


A.

Ask the project team to delay the kick-off while resolving the concern.


B.

Request a copy of the project assumptions log for more insight.


C.

Meet with the project sponsor to obtain more information.


D.

Consult with the project team members to gain their opinions.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.