PMI Project-Management-Professional PMP Question # 667 Topic 68 Discussion

PMP Exam Topic 68 Question 667 Discussion:
Question #: 667
Topic #: 68

A new development project is about to start, and the project manager knows that a high-profile customer makes very specific and frequent requests in all sprints. This project will demand contract coordination with third parties, and the project manager must find a better way to manage customer and partner expectations.

What strategy should the project manager use?


A.

Focus on the implementation of a software as a service (SaaS) solution for the customer.


B.

Specify the scope and features to be deployed in the contract clearly.


C.

Work very closely with the customer and third parties to meet their needs.


D.

Change the marketing and product management definitions to meet stakeholder needs.