PMI Project-Management-Professional PMP Question # 672 Topic 69 Discussion

PMP Exam Topic 69 Question 672 Discussion:
Question #: 672
Topic #: 69

A project team is globally distributed with team members living and working in different time zones. The project manager is trying to get the team

to collaborate effectively.

Which three actions should the project manager take to accomplish this goal? (Choose three)


A.

Require the team to have daily mandatory meetings with the project management office (PMO).


B.

Recommend the use of formal written documentation in all project communications.


C.

Review the communications strategy with the team regularly with a view for continuous improvement.


D.

Send out a survey to review the preferred method, time frequency for communications.


E.

Compile a communications management plan with input from all stakeholders and distribute for review and approval.