Question #: 679
Topic #: 69

A project manager notices that the project team is unlikely to complete the development of a system on time before the testing start date, which was based on the technical

complexity of the project. What should the project manager do before communicating with the client during the regular project progress meeting?


A.

Tell the client about the chance for the potential delay.


B.

Work with the project team to evaluate the potential delay.


C.

Do not disclose the likelihood of a delay as it is yet to happen.


D.

Ask the project sponsor to inform the client in the next update.