PMI Project-Management-Professional PMP Question # 680 Topic 69 Discussion

PMP Exam Topic 69 Question 680 Discussion:
Question #: 680
Topic #: 69

Halfway through a project, the project sponsor is replaced by another peer who was not previously engaged in the project. The new project sponsor has rejected most of the project artifacts, and the team did not get the latest increment approved on the current iteration. Stakeholders are not feeling confident about the project outcome.

What should the project manager have done to prevent this situation?


A.

Performed a stakeholder analysis when the sponsor joined the project


B.

Held a governance meeting to review the project increment


C.

Conducted a product iteration review with the new project sponsor


D.

Escalated the issue to ensure the increment would be approved


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer: