PMI Project-Management-Professional PMP Question # 682 Topic 70 Discussion

PMP Exam Topic 70 Question 682 Discussion:
Question #: 682
Topic #: 70

During a team meeting, the new agile project manager becomes aware that there are many complaints from the customer regarding project stability and other critical issues.

A team member states that the deliverables were developed by experienced employees who confirmed that the project was stable.

How should the new project manager address these concerns?


A.

Allow the agile team to decide what they are able to deliver in each iteration


B.

Ask the team for additional feedback and add tasks to the task board,


C.

Hold a brainstorming session to identify the root cause of the complaints.


D.

Document the customer's complaints and critical issues in the issue log.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.