Pre-Summer Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: validbest

Exam PMP All Questions
Exam PMP All Questions

View all questions & answers for the PMP exam

PMI Project-Management-Professional PMP Question # 683 Topic 70 Discussion

PMP Exam Topic 70 Question 683 Discussion:
Question #: 683
Topic #: 70

An agile team is facing a challenge with the quality of its deliverables. Every time a feature is promoted to production, many defects arise, preventing the customers from properly using the solution.

What should the project manager do to avoid this situation in the future?


A.

Create a team incentive program with prizes, allowing the team members to work overtime to find defects.


B.

Reduce the release cycle and invest more time on stabilizing the current features instead of releasing new ones.


C.

Hire a quality assurance specialist and integrate a second phase of testing into the current project life cycle.


D.

Use the next retrospective to understand the root cause of the quality issues and have the team come up with an action plan.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.