PMI Project-Management-Professional PMP Question # 684 Topic 70 Discussion

PMP Exam Topic 70 Question 684 Discussion:
Question #: 684
Topic #: 70

A telecommunications project consists of departments spread across several countries with different cultures. The project team rarely meets in person, and each team member works independently using online reporting tools.

What should the project manager do to ensure team members are committed to project success?


A.

Control and follow the project's mam goals, budget, and schedule


B.

Plan regular virtual meetings to motivate and support the team.


C.

Meet in small groups and share information by email with the rest of the team


D.

Create a monthly report so everyone will be informed of the current status.