During the testing phase of a project, the project manager is made aware that components delivered from a specific vendor have defects. However, the vendor refuses to fix the defects because it will incur additional costs for them.

What should the project manager do next?


A.

Ask the vendor for revised timelines and cost needs.


B.

Review the acceptance criteria defined with the vendor.


C.

Communicate with the vendor for contract changes.


D.

Request cancellation of the contract with the vendor.