PMI Project-Management-Professional PMP Question # 854 Topic 87 Discussion

PMP Exam Topic 87 Question 854 Discussion:
Question #: 854
Topic #: 87

During the execution phase of a large project there is an extremely high number of change requests Because of this the project manager realizes that there is a greater risk for rejection of the deliverables

How should the project manager mitigate this risk without compromising the completion date?


A.

Review the integrated change control process to restrict the number of changes


B.

Focus on delivering incremental value through multiple smaller deliveries


C.

Request sponsor support to get buy-in from the users and stakeholders


D.

Restart the stakeholder engagement process by collecting user requirements again